A perimeter radar site acceptance test should show that a required event makes it from the radar to the operator. A track on the map is one part of that result. For a system with camera verification, the same test also needs to show that the platform raised the correct alarm and that the operator received a usable view of the event. Record these outcomes separately so the handover report identifies exactly what passed.
1. Agree on the pass criteria before the test
Use the approved site plan and project requirements to list the zones under test. For each case, define the expected radar observation, the alarm rule, the destination console and the required camera view or recording. If an alarm or usable image must be available by a particular time or location, agree on that boundary and the event that starts the clock. Record the installed configuration, including the zone map revision, active rule and camera mapping.
Include both an alarm case and a control case wherever the project requires the system to distinguish between them. For example, a supervised passage in an alarm zone may require an event, while normal movement in an adjacent authorised area may be tracked without generating one. Specify the expected outcome before the walk. Use the perimeter radar placement guide to review physical coverage and confirm the approved test routes.
2. Record the same test at all three stages
Give each run a unique test ID. Have one person document when the agreed reference event occurred and another review the operator console. Save the radar record, the alarm log and the associated video for that same run. Record the source device and track ID where available, then associate them with the platform event ID. Confirm the clock and time zone used by each log before comparing timestamps.

Check the radar track, the platform alarm and the camera evidence for the same test run.
- Radar track. Confirm that the expected person or object was tracked in the required area. Record the source, track ID and relevant observation time.
- Platform alarm. Confirm that the expected rule generated the correct event for the zone and that it reached the specified operator interface. Record the event ID and the time the alarm became available there.
- Camera verification. Confirm that the event opened the correct live view or linked the right recording, as specified for the project. Record when the operator could first verify the required activity. A camera command timestamp alone does not establish when a usable image became available.
Measure each required interval from the agreed start event. A line crossing and a subsequent rule condition, such as a required dwell time, mark different instants. If clock alignment is uncertain relative to the allowed response time, repeat the timing check with a common reference before signing off. The perimeter radar integration guide shows how to use these records to identify the first stage that failed.
3. Use one acceptance record per test run
The example below shows how a test can pass the first two stages and fail verification. The acceptance limits for your site should come from the agreed project requirements.
| Field | Example entry |
|---|---|
| Test ID and configuration | SAT-07, Zone B, approved map revision 3 and camera preset 02. |
| Expected result | Track the authorised test participant, raise a Zone B alarm and display a view that lets the operator verify the event. |
| Radar evidence | Pass. The expected track was recorded in Zone B. Attach the source record and track ID. |
| Platform evidence | Pass. The correct alarm appeared on the operator console. Attach the event ID and log entry. |
| Camera evidence | Fail. The alarm opened a view of the wrong area. Attach the displayed clip and log the observed camera preset. |
| Disposition | Fail the end-to-end case. Correct the event-to-camera assignment and repeat SAT-07 using the same expected result. |
Keep separate fields for expected outcome, observed outcome and pass or fail. Use Not applicable for a stage that the requirements explicitly exclude from that case. Use Not tested for an outstanding check. Keep unavailable evidence visible in the report so the reviewer can distinguish it from a verified pass.
4. Verify normal operation and repeat failed cases
Run the approved cases under the operating conditions specified for handover. If the project requires night operation, repeat the relevant tests with the normal night camera settings and lighting. Keep false alarms, missed alarms and unavailable verification images as separate findings. An alarm list that looks quiet is meaningful only alongside successful required-event tests. For unwanted events, see the perimeter radar false-alarm troubleshooting guide.
After a correction, repeat the original test with the same expected result and rerun related cases that share the changed setting. For example, after correcting a camera preset mapping, check other zones that use the same camera. If the event selects the correct camera but the view is consistently offset or late, use the radar-to-PTZ troubleshooting guide to investigate alignment and timing.
5. Hand over the result, evidence and tested configuration
Summarise which zones, scenarios and operating conditions were tested, which passed, and what remains open. Give each open item an owner and a retest requirement. Hand over the final zone map, rule and camera mappings, test records and supporting logs or clips in accordance with the site’s data-handling policy. Mark the configuration revision that the evidence actually covers.
For an integrated perimeter radar system, agree with the integrator on where radar data, alarm events and camera evidence can be recorded before arriving on site. The MSR-S200 perimeter radar provides target data to the connected system. Verify the alarm and camera behaviour against the platform and configuration supplied for the project.